Roads22D00008

CONSTRUCTION OF BATANGAS ACCESS ZONE - WEST SIDE (PHASE 1), BATANGAS CITY, SAN PASCUAL AND BAUAN, BATANGAS

CONSTRUCTION OF BATANGAS ACCESS ZONE - WEST SIDE (PHASE 1), BATANGAS CITY, SAN PASCUAL AND BAUAN, BATANGAS is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱260,549,255.25. Status: Reported complete (DPWH). Contractor on record: TCSC CORP. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

221 projects · ₱15.7B total · 0 flags

Other projects by this contractor

View all 221 projects →

4. Implementation

Contract Amount

₱260,549,255.25

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

December 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.