Roads20DN0200

OPENING AND CONCRETING OF BRGY. MACAMOT TO BRGY. TATALA FMR, BRGY. MACAMOT TO BRGY. TATALA BINANGONAN, RIZAL

OPENING AND CONCRETING OF BRGY. MACAMOT TO BRGY. TATALA FMR, BRGY. MACAMOT TO BRGY. TATALA BINANGONAN, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱9,746,888.00. Status: Reported complete (DPWH). Contractor on record: FRANZCOR TRADING. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement/Construction of Flood Control Structures of Antipolo River, Brgy. Muntindilaw and Mambugan, Antipolo City, Rizal
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Rizal 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,746,888.00

Progress

Reported complete (DPWH)

Start Date

May 27, 2021

Target End

August 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.