Buildings and Facilities16DP0021

CONSTRUCTION OF DEL REMEDIO NATIONAL HIGH SCHOOL, SAN PABLO CITY, LAGUNA THREE (3) STOREY SIX (6) CLASSROOM

CONSTRUCTION OF DEL REMEDIO NATIONAL HIGH SCHOOL, SAN PABLO CITY, LAGUNA THREE (3) STOREY SIX (6) CLASSROOM is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱11,043,593.54. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Projects based on Flood Master Plan for Metro Manila and Surrounding Areas - Construction of Flood Control Structure (Upstream and Downstream) of Malaunod Bridge, San Pablo City, Laguna 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-16-0030618

₱655,280.00 · FY2016

Released to Zamboanga Sibugay National High School (Pangi Re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱11,043,593.54

Progress

Reported complete (DPWH)

Start Date

July 6, 2016

Target End

March 2, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.