Water Provision and Storage24J00279

IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II, BRGY. KAGAY, SULU

IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II, BRGY. KAGAY, SULU is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱9,945,003.20. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: AHSB CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,945,003.20

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

December 11, 2024

Target End

March 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.