Construction of Flood Mitigation Structure24K00134

Construction of Flood Control Structure along Sagayaran River (Upstream) of Nabaliwa Bridge, Package 3, Pangantucan, Bukidnon

Construction of Flood Control Structure along Sagayaran River (Upstream) of Nabaliwa Bridge, Package 3, Pangantucan, Bukidnon is a DPWH-tracked public work in PANGANTUCAN (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱70,727,334.57. Status: Reported complete (DPWH). Contractor on record: C'ZARLES CONST & SUPPLY. Figures trace to sumbong.

PANGANTUCAN (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱31,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Barandias - Dominorog Rd ( Upstream ) of Dominorog Bridge, Talakag, Bukidnon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bukidnon 4th District Engineering Office · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

59 projects · ₱4.2B total · 5 flags

4. Implementation

Contract Amount

₱70,727,334.57

Progress

Reported complete (DPWH)

Start Date

May 3, 2024

Target End

February 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.