Flood Control and Drainage25GH0144

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY MANGOROCORO, AJUY, ILOILO

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY MANGOROCORO, AJUY, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱143,220,914.05. Status: Past target date (DPWH On-Going). Contractor on record: C'ZARLES CONST & SUPPLY. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Barrido, Ajuy, Iloilo
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-25-0019468

₱-7,848,864.00 · FY2025

Released to Bicol Region General Hospital and Geriatric Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

59 projects · ₱4.2B total · 5 flags

Other projects by this contractor

View all 59 projects →

4. Implementation

Contract Amount

₱143,220,914.05

Progress

Past target date (DPWH On-Going)

Start Date

May 26, 2025

Target End

March 20, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.