CONSTRUCTION OF SAYRE HIGHWAY PARALLEL ROAD, MARAMAG SECTION, PACKAGE 1, MARAMAG, BUKIDNON

CONSTRUCTION OF SAYRE HIGHWAY PARALLEL ROAD, MARAMAG SECTION, PACKAGE 1, MARAMAG, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱188,727,746.66. Status: Past target date (DPWH On-Going). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱188,727,746.66

Progress

Past target date (DPWH On-Going)

Start Date

December 26, 2024

Target End

April 19, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.