Construction of Drainage Structure23OB0034

Construction of Box Culvert along Summer Homes, Barangay Concepcion Uno, Marikina City

Construction of Box Culvert along Summer Homes, Barangay Concepcion Uno, Marikina City is a DPWH-tracked public work in CITY OF MARIKINA (METROPOLITAN MANILA), MARIKINA CITY, National Capital Region. Reported contract value: ₱46,546,399.20. Status: Reported complete (DPWH). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC. Figures trace to sumbong.

CITY OF MARIKINA (METROPOLITAN MANILA), MARIKINA CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Bank of Creek in Barangay 163, (Phase 3), Caloocan City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

231 projects · ₱7.1B total · 9 flags

4. Implementation

Contract Amount

₱46,546,399.20

Progress

Reported complete (DPWH)

Start Date

February 6, 2023

Target End

December 1, 2024