Buildings and Facilities22FN0001

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT DPWH COMPOUND, BARANGAY STA. TERESITA, BAAO, CAMARINES SUR

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT DPWH COMPOUND, BARANGAY STA. TERESITA, BAAO, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱2,917,468.25. Status: Reported complete (DPWH). Contractor on record: HILLSIDE CONST CORP FORMERLY: HILLSIDE CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Balos River Flood Mitigation Structure (Downstream), Barangay San Francisco, Iriga City, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camarines Sur 5th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

35 projects · ₱197.0M total · 0 flags

4. Implementation

Contract Amount

₱2,917,468.25

Progress

Reported complete (DPWH)

Start Date

February 18, 2022

Target End

April 18, 2022