Roads20IL0053

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO FATIMA HILLS, ICHON, MACROHON, SOUTHERN LEYTE

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO FATIMA HILLS, ICHON, MACROHON, SOUTHERN LEYTE is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱11,505,200.00. Status: Reported complete (DPWH). Contractor on record: JONATHAN B BAUTISTA ENT. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Amparo Flood Flood Control, Macrohon, Southern Leyte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Southern Leyte 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

11 projects · ₱101.3M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES/ICHON-SINDANGAN-GUINABONAN-MANINGNING ROAD CONNECTING TO SC GLOBAL MANUFACTURER, SOGOD BAY COCO ACTIVE CARBON AND KENNEMER FOODS INTERNATIONAL, MACROHON AND MALITB

Southern Leyte 1st DEO, Region VIII

2019₱20.6M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BATO - BONTOC RD. - K1113+830-K1114+225, K1116+700-K1116+800, K1117+270-K1117+440

Leyte 5th DEO, Region VIII

2021₱15.1M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BARANGAY ROAD FROM BARANGAY BULI TO BARANGAY IMELDA, BATO, LEYTE

Leyte 5th DEO, Region VIII

2020₱14.6M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS, CONSTRUCTION OF ICHON - SINDANGAN ROAD (BYPASS), BARANGAYS ICHON AND SINDANGAN, MACROHON, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2019₱9.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES AND INDUSTRIES AND ECONOMIC ZONES ICHON - SINDANGAN - GUINABONAN - MANINGNING ROAD CONNECTING TO SC GLOBAL MANUFACTURER, SOGOD BAY COCO ACTIVE CARBON AND KENNEMER FOODS INTERNATIONAL, MALITBOG, SO

Southern Leyte 1st DEO, Region VIII

2021₱9.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. STO. NIÑO, BRGY. TAGAYTAY, BRGY. SAN JUAN, BRGY. UPPER MAHAPLAG, BRGY. POBLACION, MAHAPLAG, LEYTE

Leyte 5th DEO, Region VIII

2020₱6.7M
Reported complete (DPWH)
View all 11 projects →

4. Implementation

Contract Amount

₱11,505,200.00

Progress

Reported complete (DPWH)

Start Date

February 10, 2020

Target End

December 5, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.