Roads18DD0249

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM,PREVENTIVE MAINTENANCE, TERTIARY ROADS, LIPA- BALETE RD (K0077+(-538) TO K0078+360; K0078+660 TO K0079+000; K0079+174 TO K0079+405; K0079+684 TO K0079+725)

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM,PREVENTIVE MAINTENANCE, TERTIARY ROADS, LIPA- BALETE RD (K0077+(-538) TO K0078+360; K0078+660 TO K0079+000; K0079+174 TO K0079+405; K0079+684 TO K0079+725) is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱22,312,684.66. Status: Reported complete (DPWH). Contractor on record: RUSMEN BUILDERS. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Drainage System, Brgy. Bigain 2, San Jose, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

107 projects · ₱3.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), MUNICIPALITY OF SAN PASCUAL, BATANGAS (PHASE 2)

Batangas 2nd DEO, Region IV-A

2023₱148.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, ASPHALT OVERLAY WITH CORRECTION 100 MM BATANGAS - QUEZON RD K0134-898 - K0136+465, K0136+497 - K0136+909

Batangas 2nd DEO, Region IV-A

2024₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE L, BATANGAS

Batangas 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - PRIMARY ROADS, MANILA-BATANGAS RD - K0073 + 500 - K0076 +000

Batangas 4th DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, BAUAN-MABINI RD K0146+(-072) - K0146+726, K0146+965 - K0147+139

Batangas 2nd DEO, Region IV-A

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, LIPA-BALETE RD - K0077 + 094 - K0078 + 659, K0079 + 940 - K0081 + 240

Batangas 4th DEO, Region IV-A

2024₱84.2M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱22,312,684.66

Progress

Reported complete (DPWH)

Start Date

April 8, 2018

Target End

July 21, 2018

5. Audit