CONSTRUCTION OF MULTI-PURPOSE BUILDING SAN NICOLAS 1ST, SASMUAN, PAMPANGA

CONSTRUCTION OF MULTI-PURPOSE BUILDING SAN NICOLAS 1ST, SASMUAN, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱2,969,895.42. Status: Reported complete (DPWH). Contractor on record: MCB ZAMORA CONST. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,969,895.42

Progress

Reported complete (DPWH)

Start Date

September 30, 2020

Target End

January 27, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.