Roads18L00076

WIDENING (4 INTO 6 LANES) OF SURGIAO-DAVAO COASTAL RD INCL. ROW (BRGY. APOKON SECT.) DVO. DEL NORTE

WIDENING (4 INTO 6 LANES) OF SURGIAO-DAVAO COASTAL RD INCL. ROW (BRGY. APOKON SECT.) DVO. DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱156,469,844.40. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST 7040. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱156,469,844.40

Progress

Reported complete (DPWH)

Start Date

July 31, 2018

Target End

November 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.