Buildings and Facilities25PL0053

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY CAMALOG, BAYAO, WAGUD, LIMOS, PINUKPUK, KALINGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY CAMALOG, BAYAO, WAGUD, LIMOS, PINUKPUK, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱9,653,045.36. Status: Past target date (DPWH On-Going). Contractor on record: FOUR-G CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Mananig River at Cullayanan, Barangay Junction, Pinukpuk, Kalinga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lower Kalinga DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

18 projects · ₱204.9M total · 0 flags

Other projects by this contractor

View all 18 projects →

4. Implementation

Contract Amount

₱9,653,045.36

Progress

Past target date (DPWH On-Going)

Start Date

June 27, 2025

Target End

October 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.