Flood Control and Drainage17O00022

VALENZUELA-OBANDO MEYCAUAYAN FLOOD CONTROL PROJECT NAVOTAS-PROVISION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE (CONSTRUCTION OF PUMPING STATION WITH BOX CULVERT ALONG COASTAL DIKE), NAVOTAS CITY

VALENZUELA-OBANDO MEYCAUAYAN FLOOD CONTROL PROJECT NAVOTAS-PROVISION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE (CONSTRUCTION OF PUMPING STATION WITH BOX CULVERT ALONG COASTAL DIKE), NAVOTAS CITY is a DPWH-tracked public work in Flood Control Management Cluster, Central Office. Reported contract value: ₱89,770,023.96. Status: Reported complete (DPWH). Contractor on record: PETER G CHUA BUILDERS. Figures trace to dpwh.

Flood Control Management Cluster, Central Office
Region: Central Office

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱89,770,023.96

Progress

Reported complete (DPWH)

Start Date

December 18, 2017

Target End

June 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.