Buildings and Facilities19BG0012

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING (COVERED COURT) BRGY. GADDANAN, SAN MATEO, ISABELA

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING (COVERED COURT) BRGY. GADDANAN, SAN MATEO, ISABELA is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱1,484,851.76. Status: Reported complete (DPWH). Contractor on record: BDA JR CONST. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-19-0009961

₱-37,000,000.00 · FY2019

Released to Rizal 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

19BG0012-Local Infrastructure Program - Constructi

₱1,410,645.55 · BDA JR CONSTRUCTION

4. Implementation

Contract Amount

₱1,484,851.76

Progress

Reported complete (DPWH)

Start Date

June 17, 2019

Target End

September 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.