Water Provision and Storage20BC0191

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM, (ZITANGA ES, BALLESTEROS), (ABBANGKERUAN ES, PAMPLONA), (BALINGIT ES, PAMPLONA), (LIPATAN INTEGRATED SCHOOL, STO. NIÑO), (LATTAC ES, STO. NIÑO), (AMMUBUAN ES, BALLESTEROS), (DIBALLO ES, CLAVERIA), (DUGO ES, AB

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM, (ZITANGA ES, BALLESTEROS), (ABBANGKERUAN ES, PAMPLONA), (BALINGIT ES, PAMPLONA), (LIPATAN INTEGRATED SCHOOL, STO. NIÑO), (LATTAC ES, STO. NIÑO), (AMMUBUAN ES, BALLESTEROS), (DIBALLO ES, CLAVERIA), (DUGO ES, AB is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱4,027,444.97. Status: Reported complete (DPWH). Contractor on record: REGIGAR CONST. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canayun-Sirit-Dana-ili Flood Control Along Abulug River ,Abulug,Cagayan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cagayan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,027,444.97

Progress

Reported complete (DPWH)

Start Date

July 3, 2020

Target End

October 30, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.