Roads21FB0190

CONCRETING OF BRGY. MINA TO BRGY. GOTOB TO BRGY. LIGBAN FMR, BRGY. MINA, BRGY. GOTOB AND BRGY. LIGBAN, CAMALIG, ALBAY

CONCRETING OF BRGY. MINA TO BRGY. GOTOB TO BRGY. LIGBAN FMR, BRGY. MINA, BRGY. GOTOB AND BRGY. LIGBAN, CAMALIG, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱14,375,380.02. Status: Past target date (DPWH On-Going). Contractor on record: NICATHIR CONST AND SUPPLY CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱23,100,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation/Improvement of Flood Control, Sua-Tumpa-Libod River (Libod Section), Brgy. Libod, Camalig, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,375,380.02

Progress

Past target date (DPWH On-Going)

Start Date

July 14, 2021

Target End

December 1, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.