Bridges15KJ0135

WIDENING OF BRIDGES TO MORE THAN 2 LANES, TUDELA BRIDGE (B01139MN) ALONG OZAMIZ-OROQUIETA ROAD (COMPLETION), TUDELA, MIS. OCC.

WIDENING OF BRIDGES TO MORE THAN 2 LANES, TUDELA BRIDGE (B01139MN) ALONG OZAMIZ-OROQUIETA ROAD (COMPLETION), TUDELA, MIS. OCC. is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱33,075,634.33. Status: Reported complete (DPWH). Contractor on record: THOM-ARMAN CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱33,075,634.33

Progress

Reported complete (DPWH)

Start Date

November 21, 2016

Target End

May 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.