Water Provision and Storage20JG0074

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/RAIN WATER COLLECTOR SYSTEM,

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/RAIN WATER COLLECTOR SYSTEM, is a DPWH-tracked public work in Zamboanga del Sur 2nd DEO, Region IX. Reported contract value: ₱4,067,007.87. Status: Reported complete (DPWH). Contractor on record: JZL BUILDERS. Figures trace to dpwh.

Zamboanga del Sur 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Damit Flood Control Project, Brgy. Damit, Bayog, Zamboanga del Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Zamboanga del Sur 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20JG0074

₱4,067,007.87 · JZL BUILDERS AND ENTERPRISES

Contractor

B

81 projects · ₱732.4M total · 0 flags

4. Implementation

Contract Amount

₱4,067,007.87

Progress

Reported complete (DPWH)

Start Date

July 15, 2020

Target End

August 23, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.