Flood Control and Drainage20FO0077

REHABILITATION/IMPROVEMENT OF MAROCMOC BRIDGE FLOOD CONTROL STRUCTURE (RIGHT SIDE FACING UPSTREAM AND LEFT SIDE FACING DOWNSTREAM OF MAROCMOC BRIDGE) IN LIBON, ALBAY

REHABILITATION/IMPROVEMENT OF MAROCMOC BRIDGE FLOOD CONTROL STRUCTURE (RIGHT SIDE FACING UPSTREAM AND LEFT SIDE FACING DOWNSTREAM OF MAROCMOC BRIDGE) IN LIBON, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: ELKANKONSTRAK DEVELOPMENT CORP. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Marocmoc Bridge Flood Control Structure (Right Side Facing Upstream and Left Side Facing Downstream of Marocmoc Bridge) in Libon, Albay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Albay 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

57 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2024₱141.3M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2023₱140.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD - SECONDARY ROADS - ALBAY WEST COAST ROAD (MARIGONDON SECTION), KO551 + 680.00 - KO552 + 1

Albay 3rd DEO, Region V

2024₱140.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-GUINOBATAN-JOVELLAR-DONSOL ROAD LEADING TO PILAR PORT, GUINOBATAN AND JOVELLAR, ALBAY, GU

Region V, Region V

2023₱102.4M
Past target date (DPWH On-Going)

Construction of Revetment along Downstream of Hamorawon Bridge, Pili, Camarines Sur

PILI (CAPITAL) (CAMARINES SUR), CAMARINES SUR, Region V

2023₱95.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱93.6M
Past target date (DPWH On-Going)
View all 57 projects →

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

November 9, 2020

Target End

April 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.