Buildings and Facilities22NF0102

A. REHABILITATION/IMPROVEMENT OF DPWH D.E. QUARTERS, DPWH, SURIGAO DEL NORTE,1ST DEO, BRGY. POB. 12, DAPA, SURIGAO DEL NORTE; B. REHABILITATION/IMPROVEMENT OF DPWH FENCE, DPWH, SURIGAO DEL NORTE 1ST DEO, BRGY. POB. 12, DAPA, SURIGAO DEL NORTE; C. REHABILI

A. REHABILITATION/IMPROVEMENT OF DPWH D.E. QUARTERS, DPWH, SURIGAO DEL NORTE,1ST DEO, BRGY. POB. 12, DAPA, SURIGAO DEL NORTE; B. REHABILITATION/IMPROVEMENT OF DPWH FENCE, DPWH, SURIGAO DEL NORTE 1ST DEO, BRGY. POB. 12, DAPA, SURIGAO DEL NORTE; C. REHABILI is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱20,246,373.47. Status: Reported complete (DPWH). Contractor on record: CARTESIAN BUILDERS CORP FORMERLY: CARTESIAN BUILDERS. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dapja-Katunggan Flood Control Structure, Tagana-an, Surigao del Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Surigao del Norte 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

169 projects · ₱2.8B total · 4 flags

4. Implementation

Contract Amount

₱20,246,373.47

Progress

Reported complete (DPWH)

Start Date

April 15, 2022

Target End

October 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.