Roads20N00124

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS- DINAGAT- LORETO ROAD- K0001+(-146)- K0001+102.5, DINAGAT, DINAGAT ISLANDS

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS- DINAGAT- LORETO ROAD- K0001+(-146)- K0001+102.5, DINAGAT, DINAGAT ISLANDS is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱53,074,946.23. Status: Reported complete (DPWH). Contractor on record: NORTH TECH BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱53,074,946.23

Progress

Reported complete (DPWH)

Start Date

March 5, 2021

Target End

October 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.