Roads25OB0201

REHABILITATION OF ROAD AT ST. JAMES, ST. CATHERINE, ST. RITA, AND ST. FRANCIS AT PERPETUAL VILLAGE, TANYAG, TAGUIG CITY

REHABILITATION OF ROAD AT ST. JAMES, ST. CATHERINE, ST. RITA, AND ST. FRANCIS AT PERPETUAL VILLAGE, TANYAG, TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱18,384,534.19. Status: Past target date (DPWH On-Going). Contractor on record: GR FEVIDAL CONST DEVELOPERS CORP. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,384,534.19

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

June 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.