Water Provision and Storage23KC0112

CONSTRUCTION OF SOLAR WATER SYSTEM AT BARANGAY BARANDIAS MUNICIPALITY OF PANGANTUCAN, PROVINCE OF BUKIDNON

CONSTRUCTION OF SOLAR WATER SYSTEM AT BARANGAY BARANDIAS MUNICIPALITY OF PANGANTUCAN, PROVINCE OF BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: PETRINA CONST. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱29,510,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sagayaran River (Upstream) of Nabaliwa Bridge with Slope Protection, Pangantucan, Package 1, Bukidnon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bukidnon 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

July 10, 2023

Target End

November 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.