Flood Control and Drainage17K00018

REHAB./OF FLOOD CONTROL STRUCT. ALONG SH W/SLOPE PROT.,ALAE-KISOLON SECT.,MALUKO,MF,BUK 1ST LD

REHAB./OF FLOOD CONTROL STRUCT. ALONG SH W/SLOPE PROT.,ALAE-KISOLON SECT.,MALUKO,MF,BUK 1ST LD is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱48,121,731.47. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱48,121,731.47

Progress

Reported complete (DPWH)

Start Date

March 7, 2017

Target End

October 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.