Bridges24K00299

CONSTRUCTION OF BRIDGE AND APPROACHES, JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD-COTABATO BDRY) TO BRGY. GUTAPOL - BRGY. NEW KIDAPAWAN- BRGY. BAGOR ROAD, KIBAWE, BUKIDNON (BRGY. NEW KIDAPAWAN, KIBAWE - BRGY. BAGOR, KADINGILAN SECTION, PACKAGE II)

CONSTRUCTION OF BRIDGE AND APPROACHES, JCT. SAYRE HIGHWAY (JCT. BUKIDNON-DAVAO CITY RD-COTABATO BDRY) TO BRGY. GUTAPOL - BRGY. NEW KIDAPAWAN- BRGY. BAGOR ROAD, KIBAWE, BUKIDNON (BRGY. NEW KIDAPAWAN, KIBAWE - BRGY. BAGOR, KADINGILAN SECTION, PACKAGE II) is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱94,436,533.43. Status: Past target date (DPWH On-Going). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱94,436,533.43

Progress

Past target date (DPWH On-Going)

Start Date

July 25, 2024

Target End

May 20, 2025

5. Audit