Buildings and Facilities18DQ0137

CONSTRUCTION/ REPAIR/ RENOVATION/ UPGRADING/ EXPANSION OF MOLINO II BHS, BACOOR, CAVITE, CONSTRUCTION/ REPAIR/ RENOVATION/ UPGRADING/ EXPANSION OF BHS AND PROVISION OF EQUIPMENT MOLINO I, BACOOR, CAVITE AND CONSTRUCTION OF BHS, SAN NICOLAS III (GREEN VALL

CONSTRUCTION/ REPAIR/ RENOVATION/ UPGRADING/ EXPANSION OF MOLINO II BHS, BACOOR, CAVITE, CONSTRUCTION/ REPAIR/ RENOVATION/ UPGRADING/ EXPANSION OF BHS AND PROVISION OF EQUIPMENT MOLINO I, BACOOR, CAVITE AND CONSTRUCTION OF BHS, SAN NICOLAS III (GREEN VALL is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱3,280,511.31. Status: Reported complete (DPWH). Contractor on record: ALMAKAR BUILDERS. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱3,280,511.31

Progress

Reported complete (DPWH)

Start Date

February 20, 2019

Target End

May 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.