Flood Control and Drainage25A00416

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BUCONG-BAGAR-VILLARICA FLOOD CONTROL, CANDON CITY, ILOCOS SUR

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BUCONG-BAGAR-VILLARICA FLOOD CONTROL, CANDON CITY, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱18,720,963.18. Status: Past target date (DPWH On-Going). Contractor on record: FIRST NORTHWAY DEVELOPMENT. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,720,963.18

Progress

Past target date (DPWH On-Going)

Start Date

April 7, 2025

Target End

September 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.