Flood Control and Drainage24FA0060

CONSTRUCTION OF SAN LORENZO- SALVACION SEAWALL, TABACO CITY, ALBAY

CONSTRUCTION OF SAN LORENZO- SALVACION SEAWALL, TABACO CITY, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱109,045,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: SANRHO BUILDERS INC FOR SANRHO CONST AND SUPPL 24213. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V
Skipped: this map coordinate is shared by many projects, so the pin may not mark the exact worksite.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tobgon Flood Mitigation Structure, Ligao City, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 24213

74 projects · ₱4.2B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ESPERANZA-PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE, ESPERANZA, MASBATE(3RD LEGISLAT

Region V, Region V

2020₱159.2M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY PAWA AN

Region V, Region V

2024₱149.6M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO270+760 - KO274+300, CAMARINES NORTE

Region V, Region V

2016₱146.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ESPERANZA-PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE, ESPERANZA, MASBATE(3RD LEGISLATI

Region V, Region V

2021₱135.7M
Reported complete (DPWH)

CLUSTER 6-CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG KABILUGAN/VELASCO/BATO RIVER BASIN (LAKE BICOL), MATAGBAC, PAWA, BUANG, TABACO CTY AND CONSTRUCTION OF BONGABONG RIVER CONTROL, TABACO CITY, ALBAY

Albay 1st DEO, Region V

2024₱132.8M
Reported complete (100% progress, DPWH status On-Going)

REHABILITATION/RESTORATION OF BUYUAN FLOOD CONTROL DIKE (DOWNSTREAM OF SPILLWAY), BUYUAN, LEGAZPI CITY, ALBAY 2ND LEGISLATIVE DISTRICT

Region V, Region V

2020₱120.0M
Reported complete (DPWH)
View all 74 projects →

4. Implementation

Contract Amount

₱109,045,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

September 23, 2024

Target End

June 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.