GAA 2016 MFO-116F00047No coordinates published by DPWH

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO270+760 - KO274+300, CAMARINES NORTE

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO270+760 - KO274+300, CAMARINES NORTE is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱146,233,593.69. Status: Reported complete (DPWH). Contractor on record: SANRHO BUILDERS INC FOR SANRHO CONST AND SUPPL. Figures trace to dpwh.

Region V, Region V

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region V

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 16F00047 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO270+760 - KO274+300, CAMARINES NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

83 projects · ₱4.9B total · 4 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ESPERANZA-PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE, ESPERANZA, MASBATE(3RD LEGISLAT

Region V, Region V

2020₱159.2M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY PAWA AN

Region V, Region V

2024₱149.6M
Reported complete (DPWH)

Construction of Baranghawon River Control, Barangay Baranghawon, Tabaco City, Albay

CITY OF TABACO (ALBAY), ALBAY, Region V

2023₱144.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ESPERANZA-PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE, ESPERANZA, MASBATE(3RD LEGISLATI

Region V, Region V

2021₱135.7M
Reported complete (DPWH)

Construction of Pinagbobong River Control, Barangay Pinagbobong, Tabaco City, Albay

CITY OF TABACO (ALBAY), ALBAY, Region V

2023₱135.1M
Reported complete (DPWH)

CLUSTER 6-CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG KABILUGAN/VELASCO/BATO RIVER BASIN (LAKE BICOL), MATAGBAC, PAWA, BUANG, TABACO CTY AND CONSTRUCTION OF BONGABONG RIVER CONTROL, TABACO CITY, ALBAY

Albay 1st DEO, Region V

2024₱132.8M
Reported complete (100% progress, DPWH status On-Going)
View all 83 projects →

4. Implementation

Contract Amount

₱146,233,593.69

Progress

Reported complete (DPWH)

Start Date

August 1, 2016

Target End

April 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Not yet linked to a PSGC area.
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.