Roads17M00022

ROAD UPGRADING (UNPAVED TO PAVED) ALONG MAGPET-NOWA-DOROLOMAN-GREENFIELD ROAD, K1639+720 TO K1639+1046, (CHAINAGE 11336 TO CHAINAGE 11662), K0141+(-138) CHAINAGE 636-CHAINAGE 816), K1655+658 - K1658+084 ( CHAINAGE 14053- CHAINAGE 16479), K1665+123 - K1669

ROAD UPGRADING (UNPAVED TO PAVED) ALONG MAGPET-NOWA-DOROLOMAN-GREENFIELD ROAD, K1639+720 TO K1639+1046, (CHAINAGE 11336 TO CHAINAGE 11662), K0141+(-138) CHAINAGE 636-CHAINAGE 816), K1655+658 - K1658+084 ( CHAINAGE 14053- CHAINAGE 16479), K1665+123 - K1669 is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱138,517,503.03. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST 7040. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱138,517,503.03

Progress

Reported complete (DPWH)

Start Date

April 10, 2017

Target End

June 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.