Roads21J00014

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - IPIL CIRCUMFERENTIAL ROAD, ZAMBOANGA SIBUGAY, PHASE 2

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - IPIL CIRCUMFERENTIAL ROAD, ZAMBOANGA SIBUGAY, PHASE 2 is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱72,031,927.09. Status: Past target date (DPWH On-Going). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱72,031,927.09

Progress

Past target date (DPWH On-Going)

Start Date

March 26, 2021

Target End

September 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.