Roads17KC0023

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE ALONG SAYRE HIGHWAY K1441+906-K1442+000, K1446+081-K1446+181, K1453+180-K1453+475, MANOLO FORTICH, BUKIDNON

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE ALONG SAYRE HIGHWAY K1441+906-K1442+000, K1446+081-K1446+181, K1453+180-K1453+475, MANOLO FORTICH, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱19,057,080.00. Status: Reported complete (DPWH). Contractor on record: JT GAMOLO CONST INCORPORATION FORMERLY:J T GAMOLO CONST. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱33,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Misamis Oriental Bukidnon Agusan Road with Slope Protection, Malitbog, Bukidnon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0007288

₱2,654,000.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,057,080.00

Progress

Reported complete (DPWH)

Start Date

March 2, 2017

Target End

September 7, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.