Flood Control and Drainage20FG0060

CONSTRUCTION OF FLOOD CONTROL DIKE ALONG PARUBCAN RIVERSECTION 1 : STA.0+200.00 - STA.0+275.00 TOSECTION 4 : STA.0+080.00 - STA.0+310.00BRGY. STA. MARIA AND PILI, PRESENTACION, CAMARINES SUR

CONSTRUCTION OF FLOOD CONTROL DIKE ALONG PARUBCAN RIVERSECTION 1 : STA.0+200.00 - STA.0+275.00 TOSECTION 4 : STA.0+080.00 - STA.0+310.00BRGY. STA. MARIA AND PILI, PRESENTACION, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱77,198,578.93. Status: Reported complete (DPWH). Contractor on record: E A SANCHO CONST INC FORM E A SANCHO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱14,949,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pili (Parubcan) River, Barangay Santa Maria and Barangay Pili, Presentacion, Camarines Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Sur 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

113 projects · ₱3.8B total · 0 flags

Other projects by this contractor

View all 113 projects →

4. Implementation

Contract Amount

₱77,198,578.93

Progress

Reported complete (DPWH)

Start Date

February 27, 2020

Target End

December 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.