Roads18I00010

ASSET PRESERVATION OF NAT'L. ROADS-PREVENTIVE MAINT. BASED ON PAVEMENT MGT. SYSTEM/HIGHWAY DEV'T. & MGT.-4 (HDM-4)-TERTIARY ROADS,RAWIS-CATUBIG ROAD,KO787+(-767)-KO787+248,KO788+141-KO791+284,KO793+497-KO795+019,KO795+033-KO797+115..,NORTHERN SAMAR 2ND LD

ASSET PRESERVATION OF NAT'L. ROADS-PREVENTIVE MAINT. BASED ON PAVEMENT MGT. SYSTEM/HIGHWAY DEV'T. & MGT.-4 (HDM-4)-TERTIARY ROADS,RAWIS-CATUBIG ROAD,KO787+(-767)-KO787+248,KO788+141-KO791+284,KO793+497-KO795+019,KO795+033-KO797+115..,NORTHERN SAMAR 2ND LD is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱96,499,996.91. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱96,499,996.91

Progress

Reported complete (DPWH)

Start Date

February 9, 2018

Target End

December 5, 2018

5. Audit