Construction of Flood Mitigation Structure22FB0107

Construction of River Bank Protection Structure and Drainage System along Bugit River (Downstream Section), Imalnod, Legazpi City, Albay

Construction of River Bank Protection Structure and Drainage System along Bugit River (Downstream Section), Imalnod, Legazpi City, Albay is a DPWH-tracked public work in LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V. Reported contract value: ₱49,479,552.03. Status: Reported complete (DPWH). Contractor on record: TWINCARE BUILDERS INC / 3RB CONST & SUPPLY. Figures trace to sumbong.

LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System of Bulawan River Control (San Jose/Binitayan Section), Malilipot, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001737

₱187,700,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002950

₱120,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001730

₱80,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001631

₱60,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002890

₱2,150,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002436

₱47,688,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001623

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001966

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001965

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003024

₱50,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱49.5M total · 0 flags

4. Implementation

Contract Amount

₱49,479,552.03

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

August 19, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.