Roads20OD0138

REHABILITATION OF ROADS AND DRAINAGE ALONG E. MIRANDA ST., BRGY. PASO DE BLAS, VALENZUELA CITY

REHABILITATION OF ROADS AND DRAINAGE ALONG E. MIRANDA ST., BRGY. PASO DE BLAS, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱16,040,051.17. Status: Reported complete (DPWH). Contractor on record: CHRIZMARIE BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Creeks at Brgy. Paso De Blas, Valenzuela City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Metro Manila 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

71 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 15: 1. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BASEY - MAYDOLONG, EASTERN SAMAR; 2. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LE

Region VIII, Region VIII

2023₱247.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO KALAWIT - BARANGAY CADIAN, ORAS, EATERN SAMAR

Region VIII, Region VIII

2024₱168.8M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF MAYDOLONG - BASEY ROAD, EASTERN SAMAR

Region VIII, Region VIII

2025₱158.1M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS JCT. BUENAVISTA - LAWAAN - MARABUT RD (S00147SM), K0954+622 - K0955+000, K0955+700 - K0957+600, K0959+594 - K0960+624

Eastern Samar DEO, Region VIII

2025₱133.7M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PHASE II, BRGY. LUMATOD - DANAO, TAFT, EASTERN SAMAR

Region VIII, Region VIII

2024₱96.4M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PHASE II, BRGY. POLANGI - GAYAM, TAFT, EASTERN SAMAR LD

Region VIII, Region VIII

2024₱96.4M
Past target date (DPWH On-Going)
View all 71 projects →

4. Implementation

Contract Amount

₱16,040,051.17

Progress

Reported complete (DPWH)

Start Date

March 12, 2020

Target End

November 6, 2020

5. Audit