Bridges17EF0032

RETROFITTING/STRENGTHENING OF TIGAPLAN BR. (B00114PW) ALONG PPSR

RETROFITTING/STRENGTHENING OF TIGAPLAN BR. (B00114PW) ALONG PPSR is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱25,646,193.87. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tigaplan Flood Control, Brooke's Point, Palawan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Palawan 2nd DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

466 projects · ₱13.0B total · 1 flags

Other projects by this contractor

View all 466 projects →

4. Implementation

Contract Amount

₱25,646,193.87

Progress

Reported complete (DPWH)

Start Date

March 29, 2017

Target End

September 21, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.