Construction of Drainage Structure24CD0195

Construction of Drainage Structure, Barangay Poblacion, Norzagaray, Bulacan

Construction of Drainage Structure, Barangay Poblacion, Norzagaray, Bulacan is a DPWH-tracked public work in NORZAGARAY (BULACAN), BULACAN, Region III. Reported contract value: ₱4,865,139.76. Status: Reported complete (DPWH). Contractor on record: 1199S CONST. Figures trace to sumbong.

NORZAGARAY (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, San Jose del Monte, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0006660

₱9,979,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007287

₱1,460,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000163

₱1,078,312.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007288

₱135,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0016339

₱108,080.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

130 projects · ₱1.5B total · 0 flags

4. Implementation

Contract Amount

₱4,865,139.76

Progress

Reported complete (DPWH)

Start Date

May 16, 2024

Target End

October 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.