Buildings and Facilities18DM0104

CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT CALANTAS ES MACALELON, QUEZON

CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT CALANTAS ES MACALELON, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱12,039,500.00. Status: Reported complete (DPWH). Contractor on record: WYDERWAYS BUILDERS AND SUPPLIES. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Control along Macalelon River in Poblacion Area and Construction of Seawall in Brgy. Castillo and Luctob, Macalelon, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0032863

₱0.00 · FY2018

Released to San Roque National High Ro School (Kapitangan National High School Annex-San Roque) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

40 projects · ₱800.9M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (LUCENA GENERAL HOSPITAL), LUCENA CITY, QUEZON

Quezon 2nd DEO, Region IV-A

2024₱144.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM: NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION (COMPLETION) OF FOUR-STOREY MULTI-PURPOSE BUILDING WITH EMPLOYEE'S QUARTERS OF DPWH QUEZON 2ND DEO, DALAHICAN ROAD, BARANGAY IBABANG DUPAY, LUC

Quezon 2nd DEO, Region IV-A

2023₱86.8M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF IYAM RIVER FLOOD CONTROL (PACKAGE 3), LUCENA CITY

Quezon 2nd DEO, Region IV-A

2024₱79.1M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF IYAM RIVER FLOOD CONTROL (PACKAGE 12), LUCENA CIT

Quezon 2nd DEO, Region IV-A

2023₱77.2M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION (COMPLETION) OF 3 STOREY CAMP NAKAR STATION HOSPITAL BUILDING, SOUTHERN LUZON COMMAND, LUCENA CITY

Quezon 2nd DEO, Region IV-A

2024₱75.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, QUEZON ECO-TOURISM-SARIAYA-CANDELARIA-TIAONG-SAN ANTONIO ROAD (PACKAGE 7), QUEZON

Quezon 2nd DEO, Region IV-A

2022₱49.0M
Reported complete (DPWH)
View all 40 projects →

4. Implementation

Contract Amount

₱12,039,500.00

Progress

Reported complete (DPWH)

Start Date

November 29, 2018

Target End

June 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.