Buildings and Facilities23BD0053

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF DORMITORY AT CAGAYAN STATE UNIVERSITY (CSU) ANDREWS CAMPUS

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF DORMITORY AT CAGAYAN STATE UNIVERSITY (CSU) ANDREWS CAMPUS is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: DOUBLE J1908 CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pinacanauan River Flood Management Projects, Camasi-Centro-Dodan, Pe±ablanca, Cagayan Phase II
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cagayan 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

144 projects · ₱3.3B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO-SOLANA DIVERSION ROAD (TUGUEGARAO- SOLANA BRIDGE AND APPROACHES), PHASE 3 (PACKAGE 2), CAGAYAN

Region II, Region II

2024₱270.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - TUGUEGARAO CITY BOULEVARD (PINACANAUAN BRIDGE 2 AND APPROACHES), PHASE 3 (PACKAGE 2) TUGUEGARAO CITY, CAGAYAN

Region II, Region II

2024₱264.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - ENRILE DIVERSION ROAD (INCLUDING TUGUEGARAO - ENRILE BRIDGE AND APPROACHES, PHASE 3, CAGAYAN

Region II, Region II

2024₱237.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUGUEGARAO CIRCUMFERENTIAL DIKE ROAD, TUGUEGARA

Region II, Region II

2024₱183.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - SOLANA DIVERSION ROAD (TUGUEGARAO - SOLANA BRIDGE AND APPROACHES), PACKAGE 1, CAGAYAN

Region II, Region II

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - SOLANA DIVERSION ROAD (TUGUEGARAO - SOLANA BRIDGE AND APPROACHES), PACKAGE 2, CAGAYAN

Region II, Region II

2025₱141.7M
Past target date (DPWH On-Going)
View all 144 projects →

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

December 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.