Roads19K00051

CONSTRUCTION OF MISSING LINKS/NEW ROADS, LDNICR (SALVADOR-SAPAD-NUNUNGAN-SND SECTION), LANAO DEL NORTE

CONSTRUCTION OF MISSING LINKS/NEW ROADS, LDNICR (SALVADOR-SAPAD-NUNUNGAN-SND SECTION), LANAO DEL NORTE is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱109,664,735.25. Status: Reported complete (DPWH). Contractor on record: LANAO BUILDER AND ENT. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱109,664,735.25

Progress

Reported complete (DPWH)

Start Date

September 9, 2019

Target End

June 4, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.