Roads19AG0200

ROAD CONCRETING, SITIO GOMATO, SALUD-VICTORY, BOLINAO, PANGASINAN

ROAD CONCRETING, SITIO GOMATO, SALUD-VICTORY, BOLINAO, PANGASINAN is a DPWH-tracked public work in Pangasinan 1st DEO, Region I. Reported contract value: ₱3,761,926.23. Status: Reported complete (DPWH). Contractor on record: RAMDC CONST AND TRADING. Figures trace to dpwh.

Pangasinan 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-19-0020532

₱0.00 · FY2019

Released to Zamboanga Sibugay National High School (Pangi NHS) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

119 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES IN BALINCAGUING RIVER (BANGAN-ODA SECTION II), BRGY. BANGAN ODA, AGNO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROGRAM ALLEVIATING GAPS(SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BRIDGE CONNECTING SANTIAGO ISLAND TO BOLINAO(PACKAGEB)BOLINAO,PANGASINAN

Pangasinan 1st DEO, Region I

2024₱94.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-ROAD WIDENING-BANI-AGNO RD(KO342+790-KO345+300) AT AGNO, PANGASINAN

Pangasinan 1st DEO, Region I

2019₱77.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LUCAP BOULEVARD AND MANGROVE PARK, BRGY. BUED, ALAMINOS CITY, PANGASINAN PACKAGE II

Pangasinan 1st DEO, Region I

2023₱53.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LUCAP BOULEVARD AND MANGROVE PARK, BRGY. BUED, ALAMINOS CITY, PANGASINAN PACKAGE III

Pangasinan 1st DEO, Region I

2023₱53.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO LUCAP BOULEVARD AND MANGROVE PARK, BRGY. BUED, ALAMINOS CITY, PANGASINAN PACKAGE IV

Pangasinan 1st DEO, Region I

2023₱48.2M
Reported complete (DPWH)
View all 119 projects →

4. Implementation

Contract Amount

₱3,761,926.23

Progress

Reported complete (DPWH)

Start Date

June 27, 2019

Target End

August 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.