Construction of Flood Mitigation Structure23NH0112

Reconstruction of Flood Control Project in Barangay Ban-as, Municipality of Lianga, Surigao del Sur - Barangay Roads

Reconstruction of Flood Control Project in Barangay Ban-as, Municipality of Lianga, Surigao del Sur - Barangay Roads is a DPWH-tracked public work in LIANGA (SURIGAO DEL SUR), SURIGAO DEL SUR, Region XIII. Reported contract value: ₱134,798,744.40. Status: Reported complete (DPWH). Contractor on record: CM TAN CONST. Figures trace to sumbong.

LIANGA (SURIGAO DEL SUR), SURIGAO DEL SUR, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tago River, Brgy. Libas Gua, San Miguel, Surigao del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Surigao del Sur 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱134,798,744.40

Progress

Reported complete (DPWH)

Start Date

January 10, 2024

Target End

November 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.