Construction of Flood Mitigation Structure21OE0018

Construction of Retention Basin along Estero de Valencia Phase III, Manila City

Construction of Retention Basin along Estero de Valencia Phase III, Manila City is a DPWH-tracked public work in CITY OF MANILA, National Capital Region. Reported contract value: ₱46,940,474.10. Status: Reported complete (DPWH). Contractor on record: ST TIMOTHY CONST CORP. Figures trace to sumbong.

CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Facilities along Blumentritt, Sta. 0+000.00 to Sta. 0+297.20, Manila City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014181

₱45,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011456

₱2,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0002276

₱453,409.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007622

₱61,760,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0011029

₱311,699.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0002691

₱181,248.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0004745

₱360,594.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

942 projects · ₱44.1B total · 42 flags

Other projects by this contractor

No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0578+640 - K0578+900 R/S

Region I, Region I

2023₱390.8M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 1), ORION, BATAA

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1

Region IV-B, Region IV-B

2022₱289.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
View all 942 projects →

4. Implementation

Contract Amount

₱46,940,474.10

Progress

Reported complete (DPWH)

Start Date

June 9, 2021

Target End

November 30, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.