Roads24KG0023

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG LINAMON-ZAMBOANGA ROAD K1546+000-K1546+306, K1547+775-K1548+000, K1566+000-K1566+261, K1566+728-K1566+759, K1567+710-K1567+734, K1567+754.5-K1567+769, K1569+000-K1569+800, K1585+571-K158

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG LINAMON-ZAMBOANGA ROAD K1546+000-K1546+306, K1547+775-K1548+000, K1566+000-K1566+261, K1566+728-K1566+759, K1567+710-K1567+734, K1567+754.5-K1567+769, K1569+000-K1569+800, K1585+571-K158 is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱58,183,696.58. Status: Reported complete (DPWH). Contractor on record: LANAO BUILDER AND ENT. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure Construction of Flood Mitigation Structure along Bulod Bridge ( B00960MN ) , Upstream ( R / S ) , Tubod, Lanao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Lanao del Norte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱58,183,696.58

Progress

Reported complete (DPWH)

Start Date

May 20, 2024

Target End

January 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.