Flood Control and Drainage25GN0033

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG NAYON CREEK, SAN ENRIQUE, NEGROS OCCIDENTAL

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG NAYON CREEK, SAN ENRIQUE, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱48,233,698.04. Status: Past target date (DPWH On-Going). Contractor on record: BACHOCO CONST & SUPPLY. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Nayon Creek, San Enrique, Negros Occidental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Negros Occidental 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱48.2M total · 0 flags

4. Implementation

Contract Amount

₱48,233,698.04

Progress

Past target date (DPWH On-Going)

Start Date

April 8, 2025

Target End

December 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.