Flood Control and Drainage17PA0071

REPAIR/REHABILITATION AND IMPROVEMENT OF CATACDEGAN FLOOD CONTROL, DOWNSTREAM APPROACH B OF IKMIN BRIDGE, MANABO, ABRA

REPAIR/REHABILITATION AND IMPROVEMENT OF CATACDEGAN FLOOD CONTROL, DOWNSTREAM APPROACH B OF IKMIN BRIDGE, MANABO, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱45,954,888.00. Status: Reported complete (DPWH). Contractor on record: R U AQUINO CONST AND DEVELOPMENT CORP FO. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱39,582,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Flood Control, Sta. 0+550 - Sta. 2+100, Poblacion, La Paz, Abra
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-16-0014283

₱4,907,187.00 · FY2016

Released to Bayugan National Comprehensive High School Rele (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

133 projects · ₱12.5B total · 0 flags

4. Implementation

Contract Amount

₱45,954,888.00

Progress

Reported complete (DPWH)

Start Date

August 7, 2017

Target End

March 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.