Buildings and Facilities22BD0063

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF PALAYAG MULTI- PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), AMULUNG, CAGAYAN

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF PALAYAG MULTI- PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), AMULUNG, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,955,493.16. Status: Reported complete (DPWH). Contractor on record: ISAGA BUILDERS. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Nangalinan, Baggao, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cagayan 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱142.6M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BARREN RIVER (UPSTREAM) FLOOD CONTROL, BRGY. TALIFUGO, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2020₱19.0M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0609+175 - K0609+206, K0611+015 - K0611+036, K0611+335 - K0611+359

Apayao 1st DEO, Cordillera Administrative Region

2023₱16.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0613 + 012 - K0613 + 300

Apayao 1st DEO, Cordillera Administrative Region

2024₱14.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0623 + 742 - K0623 + 962

Apayao 1st DEO, Cordillera Administrative Region

2024₱14.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, ABBUT-CONNER RD - K0553+041 - K0553+366, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2022₱9.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, CONNER-KABUGAO RD - K0591 + 580 - K0591 + 620

Apayao 1st DEO, Cordillera Administrative Region

2024₱9.8M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱1,955,493.16

Progress

Reported complete (DPWH)

Start Date

March 23, 2022

Target End

July 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.